ABOUT WATERTOWN AIRPORT SOLAR

Watertown, New York

Convalt is developing this 100 MW solar project which would primarily sell the electricity to Convalt's Factory 1 and Factory 2 with the remainder of the electricity being sold to businesses and residences in Jefferson County located in upstate New York.

This project is located adjacent to Watertown Airport and also adjacent to the campus being developed for Convalt's manufacturing business which would produce solar cells and modules, This project will help Convalt attain 100% renewable power at its factories.

Status: Mid-Stage Development
Location: Watertown, New York
Phase 1 (Solar for Factory 1): 
Construction Start Date: May 2024
Commercial Operation Date: October 2024
Capacity: 10 MW
Phase 2 (Solar for Factory 2): 
Construction Start Date: January 2025
Commercial Operation Date: September 2025
Capacity: 90 MW
airport_img3

Project
Timeline

January
2022

Project Development

Permits & Approvals

November
2023

May
2024

Phase 1
Financial Close
Construction Start Date

Phase 1
Commercial Operation Date

October
2024

Project
Overview

Power Off-taker:

Community Solar & Direct to Consumers

Location:

Watertown Airport. NY

Surface Area:

350 acres

Commercial Operation Date:

October, 2024

Value:

$100 million

Legal Advisor:

TBD

Lenders Legal Advisor:

TBD

Lead Debt Arranger:

TBD

Master EPC:

Lincoln Infrastructure LLC

Project Status:

Date

Memorandum of Understanding (MOU)

December 2022

Power Purchase Agreement (PPA)

October 2023

Limited Notice To Proceed (LNTP)

TBD

Engineering, Procurement and Construction (EPC)

TBD

Environment and Social Impact Assessment Approval Letter

TBD

Contact us

We will be happy to answer all your questions! Convalt Energy operates multiple entities with one core mission: Make Earth Cool Again.
First Name
Last Name
Company
E-mail
Phone
Valid
Business Unit Interest
Team Interest
Country of Interest
Message
0 / 500